Cat and Fiddle repairs ‘may complete ahead of schedule’, says Derbyshire County Council
Derbyshire County Council say drainage improvements on the A54 are nearing completion and road improvements are starting soon.
In July the county council shut the A54 Macclesfield Main Road Cat and Fiddle route so £3m repairs could take place.
The work was meant to shut the road until the end of October however the council say things are going well.
A DCC spokesperson said: “We have now completed the majority of the new drainage works involving pipe connections to gullies, chambers and outfalls.


Improving the drainage is essential to prevent water collecting on the road surface which can cause potholes to form in icy weather conditions.
“These works remain on programme and are scheduled for completion by the end of the month.
“If the good weather continues, we may be able to complete the works slightly ahead of schedule.”
Since Phase 1 was started the 1.7km stretch of road has seen reflective bollards and traffic signs installed, as well as a new kerb and road drainage to help minimise surface water flooding.


As the repairs are extensive, requiring deep excavation of the existing road surface, the route will be closed until Friday October, 30.
A signed diversion route is in place to help direct road users around the works using the A54, A523, A53.
This route is the official diversion route because it provides a like-for-like route suitable for larger vehicles like lorries and buses.
However the council wanted to highlight that businesses along the A537 have been affected by the road closure for the repairs.


“We've installed additional road signs to let people know that The Cat & Fiddle Inn, Forest Distillery, Peakview Tearoom & Restaurant along with Blaze Farm and Bridge House Farm remain open as usual.
“We apologise for the delays and inconvenience while these essential repairs are underway and we'd like to thank local businesses for their patience.”
DCC said: “Please remember, for the safety of the public and the workforce, and to help ensure the project remains on schedule, the road is closed to all traffic during the works.
“Access using side roads, tracks and off-road routes is not permitted at any time. Please always follow the signed diversion routes and respect instructions from our site team.
“These restrictions are essential for maintaining a safe working environment. “Unauthorised access may compromise safety and delay progress on the project.”
This project is delivered by Derbyshire County Council and funded by the East Midlands Combined County Authority (EMCCA).
And in the spring the council will be back for Phase 2.
DCC added: “Next spring we’ll be returning for around 11 weeks to carry out further works along the route. Once again, a full road closure will be necessary.
“The works include repairing the earth banks along the road to prevent soil and rocks collapsing on to the road during bad weather. These works will also help to improve driver visibility along the route; the project will also include completing the remaining road resurfacing and finishing the project ready for road users.”