Go behind the scenes at Toddbrook Reservoir in Whaley Bridge to find out about £15m restoration project of the dam

There will be a public open day at Toddbrook Reservoir to allow residents a behind the scenes look at the £15m restoration project of the dam.
Tom Greenwood from the Canal and River Trust charity at Toddbrook Reservoir.Tom Greenwood from the Canal and River Trust charity at Toddbrook Reservoir.
Tom Greenwood from the Canal and River Trust charity at Toddbrook Reservoir.

The Canal and River Trust charity and Kier construction company will be hosting a joint public open day on Wednesday March, 15 at Toddbrook Reservoir in Whaley Bridge between 10.30am and 3.40pm.

This event will offer visitors a unique behind-the-scenes view of the two-year, £15 million restoration project that will bring the reservoir back into active use.

Hide Ad
Hide Ad

Tom Greenwood, project manager for the Canal and River Trust, said: “We are making good progress on the construction project. Kier staff have started at the top of the site and already installed around 100 steel sheet piles at the dam crest.

Tess Smith from Kier at Toddbrook Reservoir.Tess Smith from Kier at Toddbrook Reservoir.
Tess Smith from Kier at Toddbrook Reservoir.

"Further piles will be put in place over the coming months to construct the new side channel weir, tumble bay and spillway.

"These vary in size from 12 metres to 4 metres high and, once in place, the ground will be excavated to form the new channel, lined in concrete, forming a base for the new spillway structure.”

The main construction phase started last autumn and despite difficulties caused by a wet January, the plan is still to reopen the reservoir by late 2024.

Hide Ad

The project involves replacing the auxiliary spillway that was damaged in summer 2019 with a new overflow spillway structure to the north of the dam.

Hide Ad
Piling for side weir and tumble bay at Toddbrook Reservoir.Piling for side weir and tumble bay at Toddbrook Reservoir.
Piling for side weir and tumble bay at Toddbrook Reservoir.

This will include a side channel weir, ‘tumble bay’, spillway channel and stilling basin which will link into the existing bypass channel flowing into the River Goyt in the park.

To make way for the new spillway, the sailing club is being relocated behind the new tumble bay, where it will benefit from a new sailing club slipway, clubhouse, boat storage and car park.

The final phase of the project will be to remove the concrete panels from the 1970s-built overflow spillway, the dam will then be repaired and grassed over.

Hide Ad

This will be followed by works to the inlet cascade, at the far end of the reservoir, to increase resilience to high flows from Todd Brook stream.

Action stations at Toddbrook Reservoir.Action stations at Toddbrook Reservoir.
Action stations at Toddbrook Reservoir.

The project comes after the Toddbrook Reservoir crisis in 2019. Damage to the spillway was discovered on August 1, 2019 after days of heavy rain.

Hide Ad

There were fears the dam could collapse and the water could cascade down and flood the town of Whaley Bridge as well as the surrounding area.

Residents were told to leave their homes and an emergency operation to save the dam was launched involving emergency services, partner agencies and volunteers.

Hide Ad

Emergency services were drafted in from all over the country and the army and the RAF were also called in to help pump water from the 300-million-gallon reservoir.

Restoration is well under way at Toddbrook ReservoirRestoration is well under way at Toddbrook Reservoir
Restoration is well under way at Toddbrook Reservoir

The quick actions of the wonderful workers and volunteers meant the dam was saved and people could safely return to their homes just days later.

This restoration project follows extensive investigation works, two independent reports where multiple design options were explored, two public consultations and a detailed planning application.

Hide Ad

The Canal and River Trust charity, which cares for the reservoir and 2,000 miles of waterways across England and Wales, is working with its contractor Kier to deliver the restoration.

Hide Ad

Kier have created a site compound on the northern end of the town’s Memorial Park, which has been temporarily closed to the public.

New hoardings were erected last year and site accesses have been installed, and existing drainage and feeder channels are being realigned.

The public is still able to walk through the park on a footpath connecting Reservoir Road to the Memorial Park Bridge, and new children’s play equipment has been installed as a temporary measure at the top of the dam, next to Whaley Bridge Athletic Football Club.

Work on the spillway channel.Work on the spillway channel.
Work on the spillway channel.

Tom said: “We very much appreciate the patience of local residents during this phase of the project, which we expect to have finished later this summer.

Hide Ad
Hide Ad

“We are constantly monitoring noise, vibration levels and air quality at several stations across the site and appointed chartered surveyors to assess the impact.

“The closure of the main road through Whaley Bridge by Network Rail for a couple of months has caused some issues for deliveries, but we currently have an average of ten lorries per day visiting the site and they are taking alternative routes where needed.”

At the end of the project, the Memorial Park will be re-landscaped with replacement trees, wildlife habitats, extra paths and a new footbridge over the reservoir bypass channel. The project aims to achieve a net biodiversity gain of more than 10%. A new playground, similar to the previous one, will also be rebuilt at the same location.

Tom added: “With our Kier colleagues, we are looking forward to welcoming local residents and visitors to the site to find out more about this complex project. We are also planning a briefing day for local school children later this term and will hold further public open days as the works progress.”

Hide Ad

Visitors can book in advance for free, one hour guided tours onto the dam crest to view work in progress at the site.

Hide Ad

To book a free place on Kier’s Open Doors event on Wednesday 15 March, please go to the website https://opendoors.construction/ or follow the link: opendoors.construction/site/675?preview=True

Anyone who has specific construction queries or would like to receive email updates should contact Kier’s dedicated project stakeholder manager Tess Smith via email: Toddbrook@kier.co.uk.

"In these confusing and worrying times, local journalism is more vital than ever. Thanks to everyone who helps us ask the questions that matter by taking out a subscription or buying a paper. We stand together." – Phil Bramley, editor.