Rail work continues

THE end of May is the revised date for completion of the major refurbishment being undertaken at Whaley Bridge station.

Extra work was found to be necessary after it was discovered that the foundations were weaker than anticipated and new pilings have now been installed.

Whaley Bridge Town Councillor Ann Winter, updating fellow members, said: “You can’t legislate for what has happened. They are now saying it should be the end of May.”